SCHEDULES

PROJECT TIMELINE
August, 1995 Project Planning Report Completed
January, 1999 Federal Highway Administration approves Environmental Assessment/Finding of No Significant Impacts Study
June, 1999 Preliminary Design Completed
 
PROJECT PHASE SCHEDULE
Section Right of Way Utilities Construction
1 complete complete under way
US 23 Interchange complete complete 2008
2 complete complete under way
3 complete complete under way
4A complete complete under way
4B complete complete under way
5 under way under way 2007
6A under way under way 2010
6B under way under way 2011
6C under way under way 2012
7JMB complete complete underway
7A under way under way 2007
7B complete complete under way
8 under way under way 2008
9V N/A N/A 2010