SCHEDULES
| August, 1995 |
Project Planning Report Completed |
| January, 1999 |
Federal Highway Administration approves Environmental Assessment/Finding
of No Significant Impacts Study |
| June, 1999 |
Preliminary Design Completed |
| PROJECT PHASE SCHEDULE
|
| 1 |
complete |
complete |
complete |
| US 23 Interchange |
complete |
complete |
under way |
| 2 |
complete |
complete |
complete |
| 3 |
complete |
complete |
under way |
| 4A |
complete |
complete |
complete |
| 4B |
complete |
complete |
complete |
| 5 |
complete |
complete |
under way |
| 6A |
complete |
complete |
under way |
| Pond Creek Bridge |
complete |
complete |
2014 |
| 6B |
complete |
complete |
under way |
| 6C |
complete |
complete |
2016 |
| 7JMB |
complete |
complete |
complete |
| 7A |
complete |
complete |
underway |
| 7A-2 |
under way |
under way |
2015 |
| 7B |
complete |
complete |
complete |
| 8A |
under way |
under way |
2013 |
| 8B |
complete |
complete |
under way |
|