SCHEDULES

PROJECT TIMELINE
August, 1995 Project Planning Report Completed
January, 1999 Federal Highway Administration approves Environmental Assessment/Finding of No Significant Impacts Study
June, 1999 Preliminary Design Completed
 
PROJECT PHASE SCHEDULE
Section Right of Way Utilities Construction
1 complete complete complete
US 23 Interchange complete complete 2011
2 complete complete complete
3 complete complete under way
4A complete complete complete
4B complete complete complete
5 complete complete under way
6A under way under way 2013
6B under way under way 2012
6C under way under way 2014
7JMB complete complete complete
7A complete complete 2010
7B complete complete complete
8 under way under way 2011